Brick WorkCPWD DSR Civil 2023 · Item 6.3.1

Free to browse. Log in to unlock the full Rate Analysis of every Civil and Electrical item in the latest CPWD DSR.

Log in to QuickBOQ →

Brick Work — With F.P.S. bricks

All coefficients below are per 1 cum of finished work — every material, labour trade, machine, carriage line and sub-analysis this item consumes, exactly as CPWD lists them.

Complete analysis

Labour 5

IngredientQuantityUnit
Mason 1st class 0.47 day
Mason 2nd class 0.47 day
Coolie 1.8 day
Bhisti 0.2 day
Coolie 1.13 day

Machinery & Plant 1

IngredientQuantityUnit
Machine moulded perforated common burnt clay FPS (non modular) bricks of class designation 12.5 0.494 1000 Nos

Carriage 1

IngredientQuantityUnit
Carriage of Bricks 0.494 1000 Nos

Sub-Analysis (derived item) 1

IngredientQuantityUnit
[Sub-Item] 3.11 0.25 cum

Sundries & Lump Sum 2

IngredientQuantityUnit
Sundries 2.73 L.S.
Sundries 22.36 L.S.

Full DSR item description

Brick work with common burnt clay machine moulded perforated bricks of class designation 12.5 conforming to IS: 2222 in superstructure above plinth level up to floor five level in cement mortar 1:6 (1 cement : 6 coarse sand) : - With F.P.S.(non modular) bricks

Coefficients are taken from the CPWD analysis of rates for DSR Civil 2023. Basic rates are revised by cost index and correction slips, so multiply these quantities by current market rates rather than assuming a published rate is still live.

← All material coefficients|Browse CPWD DSR Civil 2023|How rate analysis works|Pricing an item not in this list|DSR vs DAR explained