Earth WorkCPWD DSR Civil 2023 · Item 2.2.1

Earth Work — All kinds of soil

Analysed rate
₹319.55per cum
CPWD analyses this item over 10 cum; the batch total is ₹3,195.50.

All coefficients below are per 10 cum of finished work. This is the complete analysis for the item — every material, labour trade, machine, carriage line and sub-analysis it consumes.

Complete analysis

Materials 1

IngredientCoefficientUnitRate (₹)Amount (₹)
Water Tanker 5 to 6 KL capacity 0.4 hour 250.00 100.00

Labour 2

IngredientCoefficientUnitRate (₹)Amount (₹)
Mate 0.004 day 816.00 3.26
Coolie 0.1 day 736.00 73.60

Machinery & Plant 4

IngredientCoefficientUnitRate (₹)Amount (₹)
Hydraulic Excavator of 1 cum bucket 1.538 hour 900.00 1,384.20
Dozer 80 HP 0.374 hour 1,700.00 635.80
Motor Grader 3.35 metre blade 0.167 hour 2,700.00 450.90
Vibratory roller 8 to 10 tonne 0.167 hour 700.00 116.90

Sundries & Lump Sum 1

IngredientCoefficientUnitRate (₹)Amount (₹)
Sundries 6.18 L.S. 2.27 14.03

Analysed rate

Sub-total (materials, labour, machinery, sundries)₹2,778.69
Add contractor's profit & overheads @ 15%₹416.80
Analysed rate for the full 10 cum batch₹3,195.50
Rate per cum₹319.55

Full DSR item description

Earth work by mechinical / manual means in rough excavation, banking excavated earth in layers not exceeding 20cm in depth, breaking clods, watering, rolling each layer with ½ tonne roller or wooden or steel rammers, and rolling every 3rd and top-most layer with power roller of minimum 8 tonnes and dressing up in embankments for roads, flood banks, marginal banks and guide banks or filling up ground depressions, lead upto 50 m and for all lift : - All kinds of soil

Coefficients are taken from the CPWD analysis of rates for DSR Civil 2023. Basic rates are revised by cost index and correction slips, so multiply these quantities by current market rates rather than assuming a published rate is still live.