Log in to QuickBOQ →All coefficients below are per 10 cum of finished work — every material, labour trade, machine, carriage line and sub-analysis this item consumes, exactly as CPWD lists them.
| Ingredient | Quantity | Unit |
|---|---|---|
| Water Tanker 5 to 6 KL capacity | 0.4 | hour |
| Ingredient | Quantity | Unit |
|---|---|---|
| Mate | 0.004 | day |
| Coolie | 0.1 | day |
| Ingredient | Quantity | Unit |
|---|---|---|
| Hydraulic Excavator of 1 cum bucket | 1.538 | hour |
| Dozer 80 HP | 0.374 | hour |
| Motor Grader 3.35 metre blade | 0.167 | hour |
| Vibratory roller 8 to 10 tonne | 0.167 | hour |
| Ingredient | Quantity | Unit |
|---|---|---|
| Sundries | 6.18 | L.S. |
Earth work by mechinical / manual means in rough excavation, banking excavated earth in layers not exceeding 20cm in depth, breaking clods, watering, rolling each layer with ½ tonne roller or wooden or steel rammers, and rolling every 3rd and top-most layer with power roller of minimum 8 tonnes and dressing up in embankments for roads, flood banks, marginal banks and guide banks or filling up ground depressions, lead upto 50 m and for all lift : - All kinds of soil
Coefficients are taken from the CPWD analysis of rates for DSR Civil 2023. Basic rates are revised by cost index and correction slips, so multiply these quantities by current market rates rather than assuming a published rate is still live.