Log in to QuickBOQ →All coefficients below are per 9.9999 sqm of finished work — every material, labour trade, machine, carriage line and sub-analysis this item consumes, exactly as CPWD lists them.
| Ingredient | Quantity | Unit |
|---|---|---|
| Stone Aggregate (Single size) : 20 mm nominal size Coarse Aggregate | 0.267 | cum |
| Stone Aggregate (Single size) : 10 mm nominal size Coarse Aggregate | 0.089 | cum |
| Coarse sand (zone III) Fine Aggregate (Sand) | 0.178 | cum |
| Stone Aggregate (Single size) : 06 mm nominal size Coarse Aggregate | 0.115 | cum |
| Portland Cement (OPC-43 Grade) Cement | 0.211 | tonne |
| Portland Cement (OPC-43 Grade) Cement | 0.02 | tonne |
| Hardening compound | 2.44 | litre |
| Ingredient | Quantity | Unit |
|---|---|---|
| Mason 2nd class | 2.15 | day |
| Beldar | 1.6 | day |
| Coolie | 1.88 | day |
| Bhisti | 0.27 | day |
| Ingredient | Quantity | Unit |
|---|---|---|
| Carriage of Stone aggregate below 40 mm nominal size | 0.356 | cum |
| Carriage of Coarse sand | 0.178 | cum |
| Carriage of Stone aggregate below 40 mm nominal size | 0.115 | cum |
| Carriage of Cement | 0.231 | tonne |
| Ingredient | Quantity | Unit |
|---|---|---|
| Carriage | 2.73 | L.S. |
| Sundries | 53.82 | L.S. |
52 mm thick cement concrete flooring with concrete hardener topping, under layer 40 mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) and top layer 12 mm thick cement hardener consisting of mix 1:2 (1 cement hardener mix : 2 graded stone aggregate 6 mm nominal size) by volume, hardening compound mixed @ 2 litre per 50 kg of cement or as per manufacturer's specifications. This includes cost of cement slurry, but excluding the cost of nosing of steps etc. complete.
Coefficients are taken from the CPWD analysis of rates for DSR Civil 2023. Basic rates are revised by cost index and correction slips, so multiply these quantities by current market rates rather than assuming a published rate is still live.