FlooringCPWD DSR Civil 2023 · Item 11.3.1

Flooring — 40 mm thick with 20 mm nominal size stone aggregate

Analysed rate
₹496.48per sqm
CPWD analyses this item over 10 sqm; the batch total is ₹4,964.80.

All coefficients below are per 10 sqm of finished work. This is the complete analysis for the item — every material, labour trade, machine, carriage line and sub-analysis it consumes.

Major materials at a glance

Coarse Aggregate
0.267cum
Stone Aggregate (Single size) : 20 mm nominal size
Coarse Aggregate
0.089cum
Stone Aggregate (Single size) : 10 mm nominal size
Fine Aggregate (Sand)
0.178cum
Coarse sand (zone III)
Cement
0.17tonne
Portland Cement (OPC-43 Grade)

Complete analysis

Materials 4

IngredientCoefficientUnitRate (₹)Amount (₹)
Stone Aggregate (Single size) : 20 mm nominal size Coarse Aggregate 0.267 cum 1,425.00 380.48
Stone Aggregate (Single size) : 10 mm nominal size Coarse Aggregate 0.089 cum 1,400.00 124.60
Coarse sand (zone III) Fine Aggregate (Sand) 0.178 cum 1,450.00 258.10
Portland Cement (OPC-43 Grade) Cement 0.17 tonne 5,156.00 876.52

Labour 3

IngredientCoefficientUnitRate (₹)Amount (₹)
Mason 2nd class 0.8 day 816.00 652.80
Beldar 1.4 day 736.00 1,030.40
Bhisti 1.04 day 816.00 848.64

Machinery & Plant 2

IngredientCoefficientUnitRate (₹)Amount (₹)
Driver for (Road roller, concrete mixer, Trucks etc.) 0.03 day 897.00 26.91
Hire charges of Concrete Mixer 0.25 to 0.40 cum with Hopper 0.03 day 900.00 27.00

Carriage 3

IngredientCoefficientUnitRate (₹)Amount (₹)
Carriage of Stone aggregate below 40 mm nominal size 0.356 cum lead-dependent
Carriage of Coarse sand 0.178 cum lead-dependent
Carriage of Cement 0.17 tonne lead-dependent

Sundries & Lump Sum 1

IngredientCoefficientUnitRate (₹)Amount (₹)
Sundries 40.43 L.S. 2.27 91.78

Analysed rate

Sub-total (materials, labour, machinery, sundries)₹4,317.22
Add contractor's profit & overheads @ 15%₹647.58
Analysed rate for the full 10 sqm batch₹4,964.80
Rate per sqm₹496.48

3 carriage lines are excluded from this total. CPWD leaves carriage rates blank because they depend on lead distance and station, so they must be priced locally and added. The analysed rate above is therefore the works cost before carriage, not a complete tender rate.

Full DSR item description

Cement concrete flooring 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate) finished with a floating coat of neat cement, including cement slurry, but excluding the cost of nosing of steps etc. complete. - 40 mm thick with 20 mm nominal size stone aggregate

Coefficients are taken from the CPWD analysis of rates for DSR Civil 2023. Basic rates are revised by cost index and correction slips, so multiply these quantities by current market rates rather than assuming a published rate is still live.