FlooringCPWD DSR Civil 2023 · Item 11.9.1

Flooring — Dark shade pigment with ordinary cement

Analysed rate
₹861.51per sqm
CPWD analyses this item over 100 sqm; the batch total is ₹86,150.63.

All coefficients below are per 100 sqm of finished work. This is the complete analysis for the item — every material, labour trade, machine, carriage line and sub-analysis it consumes.

Major materials at a glance

Coarse Aggregate
2.27cum
Stone Aggregate (Single size) : 12.5 mm nominal size
Coarse Aggregate
0.76cum
Stone Aggregate (Single size) : 10 mm nominal size
Fine Aggregate (Sand)
1.51cum
Coarse sand (zone III)
Cement
1.09tonne
Portland Cement (OPC-43 Grade)
Cement
0.2tonne
Portland Cement (OPC-43 Grade)
Cement
0.405tonne
Portland Cement (OPC-43 Grade)

Complete analysis

Materials 9

IngredientCoefficientUnitRate (₹)Amount (₹)
Stone Aggregate (Single size) : 12.5 mm nominal size Coarse Aggregate 2.27 cum 1,400.00 3,178.00
Stone Aggregate (Single size) : 10 mm nominal size Coarse Aggregate 0.76 cum 1,400.00 1,064.00
Coarse sand (zone III) Fine Aggregate (Sand) 1.51 cum 1,450.00 2,189.50
Portland Cement (OPC-43 Grade) Cement 1.09 tonne 5,156.00 5,620.04
Portland Cement (OPC-43 Grade) Cement 0.2 tonne 5,156.00 1,031.20
Marble chips up to 4 mm and down size White & black 8.72 quintal 200.00 1,744.00
Portland Cement (OPC-43 Grade) Cement 0.405 tonne 5,156.00 2,088.18
Marble dust/ powder 0.07 cum 1,180.00 82.60
Black colour dark shade pigment 28.4 kg 75.00 2,130.00

Labour 4

IngredientCoefficientUnitRate (₹)Amount (₹)
Mason 2nd class 17.9 day 816.00 14,606.40
Beldar 19.9 day 736.00 14,646.40
Bhisti 10.4 day 816.00 8,486.40
Skilled Beldar (for floor rubbing etc.) 10 day 816.00 8,160.00

Machinery & Plant 3

IngredientCoefficientUnitRate (₹)Amount (₹)
Driver for (Road roller, concrete mixer, Trucks etc.) 0.3 day 897.00 269.10
Hire charges of Concrete Mixer 0.25 to 0.40 cum with Hopper 0.3 day 900.00 270.00
Machine for rubbing of floors 16 day 350.00 5,600.00

Carriage 5

IngredientCoefficientUnitRate (₹)Amount (₹)
Carriage of Stone aggregate below 40 mm nominal size 3.03 cum lead-dependent
Carriage of Coarse sand 1.51 cum lead-dependent
Carriage of Cement 1.29 tonne lead-dependent
Carriage of Marble dust and/or marble chips 0.51 cum lead-dependent
Carriage of Cement 0.405 tonne lead-dependent

Sundries & Lump Sum 2

IngredientCoefficientUnitRate (₹)Amount (₹)
Carriage 36.4 L.S. 2.27 82.63
Sundries 1614.6 L.S. 2.27 3,665.14

Analysed rate

Sub-total (materials, labour, machinery, sundries)₹74,913.59
Add contractor's profit & overheads @ 15%₹11,237.04
Analysed rate for the full 100 sqm batch₹86,150.63
Rate per sqm₹861.51

5 carriage lines are excluded from this total. CPWD leaves carriage rates blank because they depend on lead distance and station, so they must be priced locally and added. The analysed rate above is therefore the works cost before carriage, not a complete tender rate.

Full DSR item description

40 mm thick marble chips flooring rubbed and polished to granolithic finish, under layer 34 mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 12.5 mm nominal size) and top layer 6mm thick with white, black, chocolate, grey, yellow or green marble chips of sizes from 1 mm to 4 mm nominal size, laid in cement marble powder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 4:7 (4 cement marble powder mix : 7 marble chips) by volume, including cement slurry etc. complete : - Dark shade pigment with ordinary cement

Coefficients are taken from the CPWD analysis of rates for DSR Civil 2023. Basic rates are revised by cost index and correction slips, so multiply these quantities by current market rates rather than assuming a published rate is still live.