PaintingCPWD DSR Civil 2023 · Item 13.46.1

Painting — New work

Analysed rate
₹129.83per Unit
CPWD analyses this item over 10 Unit; the batch total is ₹1,298.28.

All coefficients below are per 10 Unit of finished work. This is the complete analysis for the item — every material, labour trade, machine, carriage line and sub-analysis it consumes.

Major materials at a glance

Paint & Finishes
1.67litre
Acrylic exterior paint
Paint & Finishes
0.9litre
Acrylic Exterior Primer

Complete analysis

Materials 2

IngredientCoefficientUnitRate (₹)Amount (₹)
Acrylic exterior paint Paint & Finishes 1.67 litre 170.00 283.90
Acrylic Exterior Primer Paint & Finishes 0.9 litre 80.00 72.00

Labour 3

IngredientCoefficientUnitRate (₹)Amount (₹)
Painter 0.6 day 816.00 489.60
Coolie 0.3 day 736.00 220.80
Bhisti 0.05 day 816.00 40.80

Sundries & Lump Sum 2

IngredientCoefficientUnitRate (₹)Amount (₹)
Carriage 1.56 L.S. 2.27 3.54
Sundries 8.06 L.S. 2.27 18.30

Analysed rate

Sub-total (materials, labour, machinery, sundries)₹1,128.94
Add contractor's profit & overheads @ 15%₹169.34
Analysed rate for the full 10 Unit batch₹1,298.28
Rate per Unit₹129.83

Full DSR item description

Finishing walls with Acrylic Smooth exterior paint of required shade : - New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including priming coat of exterior primer applied @ 0.90 litre/10 sqm)

Coefficients are taken from the CPWD analysis of rates for DSR Civil 2023. Basic rates are revised by cost index and correction slips, so multiply these quantities by current market rates rather than assuming a published rate is still live.

← All material coefficients|Browse CPWD DSR Civil 2023|How rate analysis works