Plain Cement Concrete (PCC)CPWD DSR Civil 2023 · Item 4.1.3A

PCC — 1:2:4 — All work up to plinth level

Analysed rate
₹6,187.82per cum

All coefficients below are per 1 cum of finished work. This is the complete analysis for the item — every material, labour trade, machine, carriage line and sub-analysis it consumes.

Major materials at a glance

Coarse Aggregate
0.503cum
Stone Aggregate (Single size) : 20 mm nominal size
Coarse Aggregate
0.167cum
Recycled Concrete Aggregate (RCA) 20 mm nominal size
Coarse Aggregate
0.165cum
Stone Aggregate (Single size) : 10 mm nominal size
Coarse Aggregate
0.055cum
Recycled Concrete Aggregate (RCA) 10 mm nominal size
Fine Aggregate (Sand)
0.334cum
Coarse sand (zone III)
Coarse Aggregate
0.111cum
Manufactured sand derived from Recycled Concrete Aggregate (RCA)
Cement
0.32tonne
Portland Cement (OPC-43 Grade)

Complete analysis

Materials 7

IngredientCoefficientUnitRate (₹)Amount (₹)
Stone Aggregate (Single size) : 20 mm nominal size Coarse Aggregate 0.503 cum 1,425.00 716.78
Recycled Concrete Aggregate (RCA) 20 mm nominal size Coarse Aggregate 0.167 cum 957.00 159.82
Stone Aggregate (Single size) : 10 mm nominal size Coarse Aggregate 0.165 cum 1,400.00 231.00
Recycled Concrete Aggregate (RCA) 10 mm nominal size Coarse Aggregate 0.055 cum 957.00 52.64
Coarse sand (zone III) Fine Aggregate (Sand) 0.334 cum 1,450.00 484.30
Manufactured sand derived from Recycled Concrete Aggregate (RCA) Coarse Aggregate 0.111 cum 957.00 106.23
Portland Cement (OPC-43 Grade) Cement 0.32 tonne 5,156.00 1,649.92

Labour 3

IngredientCoefficientUnitRate (₹)Amount (₹)
Mason (average) 0.1 day 857.00 85.70
Beldar 1.63 day 736.00 1,199.68
Bhisti 0.7 day 816.00 571.20

Machinery & Plant 2

IngredientCoefficientUnitRate (₹)Amount (₹)
Hire charges of Concrete Mixer 0.25 to 0.40 cum with Hopper 0.07 day 900.00 63.00
Vibrator (Needle type 40 mm) 0.07 day 400.00 28.00

Carriage 3

IngredientCoefficientUnitRate (₹)Amount (₹)
Carriage of Stone aggregate below 40 mm nominal size 0.89 cum lead-dependent
Carriage of Coarse sand 0.445 cum lead-dependent
Carriage of Cement 0.32 tonne lead-dependent

Sundries & Lump Sum 1

IngredientCoefficientUnitRate (₹)Amount (₹)
Sundries 14.3 L.S. 2.27 32.46

Analysed rate

Sub-total (materials, labour, machinery, sundries)₹5,380.72
Add contractor's profit & overheads @ 15%₹807.11
Analysed rate per cum₹6,187.82

3 carriage lines are excluded from this total. CPWD leaves carriage rates blank because they depend on lead distance and station, so they must be priced locally and added. The analysed rate above is therefore the works cost before carriage, not a complete tender rate.

Full DSR item description

Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : - 1:2:4 (1 cement : 2 coarse sand (zone-III) including manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 25% : 4 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 25%)

Coefficients are taken from the CPWD analysis of rates for DSR Civil 2023. Basic rates are revised by cost index and correction slips, so multiply these quantities by current market rates rather than assuming a published rate is still live.

← All material coefficients|Browse CPWD DSR Civil 2023|How rate analysis works