Plastering & FinishingCPWD DSR Civil 2023 · Item 13.2.2

Plaster — 1:6

Analysed rate
₹309.62per Unit
CPWD analyses this item over 10 Unit; the batch total is ₹3,096.22.

All coefficients below are per 10 Unit of finished work. This is the complete analysis for the item — every material, labour trade, machine, carriage line and sub-analysis it consumes.

Complete analysis

Labour 3

IngredientCoefficientUnitRate (₹)Amount (₹)
Mason (average) 0.8 day 857.00 685.60
Coolie 0.88 day 736.00 647.68
Bhisti 0.99 day 816.00 807.84

Sub-Analysis (derived item) 1

IngredientCoefficientUnitRate (₹)Amount (₹)
[Sub-Item] 3.6 0.172 cum 3,038.50 522.62

Sundries & Lump Sum 1

IngredientCoefficientUnitRate (₹)Amount (₹)
Sundries 12.61 L.S. 2.27 28.62

Analysed rate

Sub-total (materials, labour, machinery, sundries)₹2,692.37
Add contractor's profit & overheads @ 15%₹403.86
Analysed rate for the full 10 Unit batch₹3,096.22
Rate per Unit₹309.62

Full DSR item description

15 mm cement plaster on the rough side of single or half brick wall of mix : - 1:6 (1 cement: 6 fine sand)

Coefficients are taken from the CPWD analysis of rates for DSR Civil 2023. Basic rates are revised by cost index and correction slips, so multiply these quantities by current market rates rather than assuming a published rate is still live.