Reinforced Cement Concrete (RCC)CPWD DSR Civil 2023 · Item 5.2.2

RCC — 1:1.5:3

Analysed rate
₹8,773.08per cum
CPWD analyses this item over 91.8 cum; the batch total is ₹8,05,368.94.

All coefficients below are per 91.8 cum of finished work. This is the complete analysis for the item — every material, labour trade, machine, carriage line and sub-analysis it consumes.

Major materials at a glance

Coarse Aggregate
52.326cum
Stone Aggregate (Single size) : 20 mm nominal size
Coarse Aggregate
25.704cum
Stone Aggregate (Single size) : 10 mm nominal size
Fine Aggregate (Sand)
39.015cum
Coarse sand (zone III)
Cement
36.72tonne
Portland Cement (OPC-43 Grade)

Complete analysis

Materials 4

IngredientCoefficientUnitRate (₹)Amount (₹)
Stone Aggregate (Single size) : 20 mm nominal size Coarse Aggregate 52.326 cum 1,425.00 74,564.55
Stone Aggregate (Single size) : 10 mm nominal size Coarse Aggregate 25.704 cum 1,400.00 35,985.60
Coarse sand (zone III) Fine Aggregate (Sand) 39.015 cum 1,450.00 56,571.75
Portland Cement (OPC-43 Grade) Cement 36.72 tonne 5,156.00 1,89,328.32

Labour 6

IngredientCoefficientUnitRate (₹)Amount (₹)
Beldar 112.9 day 736.00 83,094.40
Coolie 75.3 day 736.00 55,420.80
Bhisti 82.6 day 816.00 67,401.60
Mason 1st class 9.2 day 897.00 8,252.40
Mason 2nd class 9.2 day 816.00 7,507.20
Coolie 137.7 day 736.00 1,01,347.20

Machinery & Plant 2

IngredientCoefficientUnitRate (₹)Amount (₹)
Hire charges of Concrete Mixer 0.25 to 0.40 cum with Hopper 6.4 day 900.00 5,760.00
Vibrator (Needle type 40 mm) 6.4 day 400.00 2,560.00

Carriage 3

IngredientCoefficientUnitRate (₹)Amount (₹)
Carriage of Stone aggregate below 40 mm nominal size 78.03 cum lead-dependent
Carriage of Coarse sand 39.015 cum lead-dependent
Carriage of Cement 36.72 tonne lead-dependent

Sundries & Lump Sum 2

IngredientCoefficientUnitRate (₹)Amount (₹)
Sundries 1318.2 L.S. 2.27 2,992.31
Sundries 4200.3 L.S. 2.27 9,534.68

Analysed rate

Sub-total (materials, labour, machinery, sundries)₹7,00,320.82
Add contractor's profit & overheads @ 15%₹1,05,048.12
Analysed rate for the full 91.8 cum batch₹8,05,368.94
Rate per cum₹8,773.08

3 carriage lines are excluded from this total. CPWD leaves carriage rates blank because they depend on lead distance and station, so they must be priced locally and added. The analysed rate above is therefore the works cost before carriage, not a complete tender rate.

Full DSR item description

Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : - 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)

Coefficients are taken from the CPWD analysis of rates for DSR Civil 2023. Basic rates are revised by cost index and correction slips, so multiply these quantities by current market rates rather than assuming a published rate is still live.