CPWD analyses this item over 91.8 cum; the batch total is ₹7,92,693.14.
All coefficients below are per 91.8 cum of finished work. This is the complete analysis for the item — every material, labour trade, machine, carriage line and sub-analysis it consumes.
Major materials at a glance
Coarse Aggregate
41.86cum
Stone Aggregate (Single size) : 20 mm nominal size
Coarse Aggregate
10.466cum
Recycled Concrete Aggregate (RCA) 20 mm nominal size
Coarse Aggregate
20.563cum
Stone Aggregate (Single size) : 10 mm nominal size
Coarse Aggregate
5.141cum
Recycled Concrete Aggregate (RCA) 10 mm nominal size
Fine Aggregate (Sand)
31.212cum
Coarse sand (zone III)
Coarse Aggregate
7.803cum
Manufactured sand derived from Recycled Concrete Aggregate (RCA)
Cement
36.72tonne
Portland Cement (OPC-43 Grade)
Complete analysis
Materials 7
Ingredient
Coefficient
Unit
Rate (₹)
Amount (₹)
Stone Aggregate (Single size) : 20 mm nominal size Coarse Aggregate
41.86
cum
1,425.00
59,650.50
Recycled Concrete Aggregate (RCA) 20 mm nominal size Coarse Aggregate
10.466
cum
957.00
10,015.96
Stone Aggregate (Single size) : 10 mm nominal size Coarse Aggregate
20.563
cum
1,400.00
28,788.20
Recycled Concrete Aggregate (RCA) 10 mm nominal size Coarse Aggregate
5.141
cum
957.00
4,919.94
Coarse sand (zone III) Fine Aggregate (Sand)
31.212
cum
1,450.00
45,257.40
Manufactured sand derived from Recycled Concrete Aggregate (RCA) Coarse Aggregate
7.803
cum
957.00
7,467.47
Portland Cement (OPC-43 Grade) Cement
36.72
tonne
5,156.00
1,89,328.32
Labour 6
Ingredient
Coefficient
Unit
Rate (₹)
Amount (₹)
Beldar
112.9
day
736.00
83,094.40
Coolie
75.3
day
736.00
55,420.80
Bhisti
82.6
day
816.00
67,401.60
Mason 1st class
9.2
day
897.00
8,252.40
Mason 2nd class
9.2
day
816.00
7,507.20
Coolie
137.7
day
736.00
1,01,347.20
Machinery & Plant 2
Ingredient
Coefficient
Unit
Rate (₹)
Amount (₹)
Hire charges of Concrete Mixer 0.25 to 0.40 cum with Hopper
6.4
day
900.00
5,760.00
Vibrator (Needle type 40 mm)
6.4
day
400.00
2,560.00
Carriage 3
Ingredient
Coefficient
Unit
Rate (₹)
Amount (₹)
Carriage of Stone aggregate below 40 mm nominal size
3 carriage lines are excluded from this total. CPWD leaves carriage rates blank because they depend on lead distance and station, so they must be priced locally and added. The analysed rate above is therefore the works cost before carriage, not a complete tender rate.
Full DSR item description
Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : - 1:1.5:3 (1 cement : 1.5 coarse sand incuding manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%
Coefficients are taken from the CPWD analysis of rates for DSR Civil 2023. Basic rates are revised by cost index and correction slips, so multiply these quantities by current market rates rather than assuming a published rate is still live.