All coefficients below are per 1 cum of finished work. This is the complete analysis for the item — every material, labour trade, machine, carriage line and sub-analysis it consumes.
Major materials at a glance
Coarse Aggregate
0.456cum
Stone Aggregate (Single size) : 20 mm nominal size
Coarse Aggregate
0.114cum
Recycled Concrete Aggregate (RCA) 20 mm nominal size
Coarse Aggregate
0.224cum
Stone Aggregate (Single size) : 10 mm nominal size
Coarse Aggregate
0.056cum
Recycled Concrete Aggregate (RCA) 10 mm nominal size
Fine Aggregate (Sand)
0.34cum
Coarse sand (zone III)
Coarse Aggregate
0.085cum
Manufactured sand derived from Recycled Concrete Aggregate (RCA)
Cement
0.4tonne
Portland Cement (OPC-43 Grade)
Complete analysis
Materials 7
Ingredient
Coefficient
Unit
Rate (₹)
Amount (₹)
Stone Aggregate (Single size) : 20 mm nominal size Coarse Aggregate
0.456
cum
1,425.00
649.80
Recycled Concrete Aggregate (RCA) 20 mm nominal size Coarse Aggregate
0.114
cum
957.00
109.10
Stone Aggregate (Single size) : 10 mm nominal size Coarse Aggregate
0.224
cum
1,400.00
313.60
Recycled Concrete Aggregate (RCA) 10 mm nominal size Coarse Aggregate
0.056
cum
957.00
53.59
Coarse sand (zone III) Fine Aggregate (Sand)
0.34
cum
1,450.00
493.00
Manufactured sand derived from Recycled Concrete Aggregate (RCA) Coarse Aggregate
0.085
cum
957.00
81.35
Portland Cement (OPC-43 Grade) Cement
0.4
tonne
5,156.00
2,062.40
Labour 4
Ingredient
Coefficient
Unit
Rate (₹)
Amount (₹)
Mason (average)
0.24
day
857.00
205.68
Beldar
2.75
day
736.00
2,024.00
Bhisti
0.9
day
816.00
734.40
Coolie
1.5
day
736.00
1,104.00
Machinery & Plant 2
Ingredient
Coefficient
Unit
Rate (₹)
Amount (₹)
Hire charges of Concrete Mixer 0.25 to 0.40 cum with Hopper
0.08
day
900.00
72.00
Vibrator (Needle type 40 mm)
0.08
day
400.00
32.00
Carriage 3
Ingredient
Coefficient
Unit
Rate (₹)
Amount (₹)
Carriage of Stone aggregate below 40 mm nominal size
3 carriage lines are excluded from this total. CPWD leaves carriage rates blank because they depend on lead distance and station, so they must be priced locally and added. The analysed rate above is therefore the works cost before carriage, not a complete tender rate.
Full DSR item description
Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral staircases above plinth level up to floor five level excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand incuding manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20%: 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%)
Coefficients are taken from the CPWD analysis of rates for DSR Civil 2023. Basic rates are revised by cost index and correction slips, so multiply these quantities by current market rates rather than assuming a published rate is still live.