Reinforcement SteelCPWD DSR Civil 2023 · Item 5.22.2

Reinforcement Steel — Hard drawn steel wire

Analysed rate
₹77.44per kg
CPWD analyses this item over 100 kg; the batch total is ₹7,744.20.

All coefficients below are per 100 kg of finished work. This is the complete analysis for the item — every material, labour trade, machine, carriage line and sub-analysis it consumes.

Complete analysis

Materials 1

IngredientCoefficientUnitRate (₹)Amount (₹)
Hard drawn steel wire 1.05 quintal 4,800.00 5,040.00

Labour 2

IngredientCoefficientUnitRate (₹)Amount (₹)
Blacksmith 1st class 1 day 897.00 897.00
Beldar 1 day 736.00 736.00

Carriage 1

IngredientCoefficientUnitRate (₹)Amount (₹)
Carriage of Steel 0.105 tonne lead-dependent

Sundries & Lump Sum 1

IngredientCoefficientUnitRate (₹)Amount (₹)
Sundries 26.91 L.S. 2.27 61.09

Analysed rate

Sub-total (materials, labour, machinery, sundries)₹6,734.09
Add contractor's profit & overheads @ 15%₹1,010.11
Analysed rate for the full 100 kg batch₹7,744.20
Rate per kg₹77.44

1 carriage line is excluded from this total. CPWD leaves carriage rates blank because they depend on lead distance and station, so they must be priced locally and added. The analysed rate above is therefore the works cost before carriage, not a complete tender rate.

Full DSR item description

Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. - Hard drawn steel wire

Coefficients are taken from the CPWD analysis of rates for DSR Civil 2023. Basic rates are revised by cost index and correction slips, so multiply these quantities by current market rates rather than assuming a published rate is still live.

← All material coefficients|Browse CPWD DSR Civil 2023|How rate analysis works