Reinforcement SteelCPWD DSR Civil 2023 · Item 5.22.6

Reinforcement Steel — Thermo-Mechanically Treated bars of grade Fe-500D or

Analysed rate
₹87.18per kg
CPWD analyses this item over 100 kg; the batch total is ₹8,717.70.

All coefficients below are per 100 kg of finished work. This is the complete analysis for the item — every material, labour trade, machine, carriage line and sub-analysis it consumes.

Major materials at a glance

Steel
1.05quintal
Twisted steel/ deformed TMT bars Fe-500D

Complete analysis

Materials 1

IngredientCoefficientUnitRate (₹)Amount (₹)
Twisted steel/ deformed TMT bars Fe-500D Steel 1.05 quintal 5,550.00 5,827.50

Labour 2

IngredientCoefficientUnitRate (₹)Amount (₹)
Blacksmith 1st class 1 day 897.00 897.00
Beldar 1 day 736.00 736.00

Carriage 1

IngredientCoefficientUnitRate (₹)Amount (₹)
Carriage of Steel 0.105 tonne lead-dependent

Sundries & Lump Sum 2

IngredientCoefficientUnitRate (₹)Amount (₹)
Sundries 26 L.S. 2.27 59.02
Sundries 26.91 L.S. 2.27 61.09

Analysed rate

Sub-total (materials, labour, machinery, sundries)₹7,580.61
Add contractor's profit & overheads @ 15%₹1,137.09
Analysed rate for the full 100 kg batch₹8,717.70
Rate per kg₹87.18

1 carriage line is excluded from this total. CPWD leaves carriage rates blank because they depend on lead distance and station, so they must be priced locally and added. The analysed rate above is therefore the works cost before carriage, not a complete tender rate.

Full DSR item description

Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. - Thermo-Mechanically Treated bars of grade Fe-500D or more.

Coefficients are taken from the CPWD analysis of rates for DSR Civil 2023. Basic rates are revised by cost index and correction slips, so multiply these quantities by current market rates rather than assuming a published rate is still live.

← All material coefficients|Browse CPWD DSR Civil 2023|How rate analysis works