Centering & ShutteringCPWD DSR Civil 2023 · Item 5.9.6

Shuttering — Columns, Pillars, Piers, Abutments, Posts and Struts

Analysed rate
₹777.08per Unit
CPWD analyses this item over 45 Unit; the batch total is ₹34,968.49.

All coefficients below are per 45 Unit of finished work. This is the complete analysis for the item — every material, labour trade, machine, carriage line and sub-analysis it consumes.

Complete analysis

Materials 4

IngredientCoefficientUnitRate (₹)Amount (₹)
Wall form panel 1250x450 mm 1.7 each 900.00 1,530.00
Corner angle 45x45x5 mm 2.50 m long 0.85 each 275.00 233.75
Column clamp 450x1070 mm 1.063 each 1,020.00 1,084.26
Prop 2 m ( 2-3.5 m) 0.85 each 690.00 586.50

Labour 2

IngredientCoefficientUnitRate (₹)Amount (₹)
Fitter (grade 1) 10 day 897.00 8,970.00
Beldar 20 day 736.00 14,720.00

Sundries & Lump Sum 4

IngredientCoefficientUnitRate (₹)Amount (₹)
Sundries 276.2 L.S. 2.27 626.97
Carriage 520 L.S. 2.27 1,180.40
Sundries 390 L.S. 2.27 885.30
Carriage 260 L.S. 2.27 590.20

Analysed rate

Sub-total (materials, labour, machinery, sundries)₹30,407.38
Add contractor's profit & overheads @ 15%₹4,561.11
Analysed rate for the full 45 Unit batch₹34,968.49
Rate per Unit₹777.08

Full DSR item description

Centering and shuttering including strutting, propping etc. and removal of form for - Columns, Pillars, Piers, Abutments, Posts and Struts

Coefficients are taken from the CPWD analysis of rates for DSR Civil 2023. Basic rates are revised by cost index and correction slips, so multiply these quantities by current market rates rather than assuming a published rate is still live.