Centering & ShutteringCPWD DSR Civil 2023 · Item 5.9.1

Shuttering — Foundations, footings, bases of columns, etc. for mass

Analysed rate
₹316.98per Unit
CPWD analyses this item over 10 Unit; the batch total is ₹3,169.85.

All coefficients below are per 10 Unit of finished work. This is the complete analysis for the item — every material, labour trade, machine, carriage line and sub-analysis it consumes.

Complete analysis

Materials 6

IngredientCoefficientUnitRate (₹)Amount (₹)
Wall form panel 1250x500 mm 0.34 each 900.00 306.00
Corner angle 45x45x5 mm 1.50 m long 0.085 each 257.00 21.85
100 mm channel shoulder 2.5 m long 0.17 each 950.00 161.50
Double clip (bridge clip) 0.34 each 80.00 27.20
Single clip 0.17 each 64.00 10.88
M.S. tube 40 mm dia 0.213 metre 225.00 47.93

Labour 2

IngredientCoefficientUnitRate (₹)Amount (₹)
Fitter (grade 1) 0.75 day 897.00 672.75
Beldar 1.5 day 736.00 1,104.00

Sundries & Lump Sum 4

IngredientCoefficientUnitRate (₹)Amount (₹)
Sundries 22.1 L.S. 2.27 50.17
Carriage 78 L.S. 2.27 177.06
Sundries 52 L.S. 2.27 118.04
Sundries 26 L.S. 2.27 59.02

Analysed rate

Sub-total (materials, labour, machinery, sundries)₹2,756.39
Add contractor's profit & overheads @ 15%₹413.46
Analysed rate for the full 10 Unit batch₹3,169.85
Rate per Unit₹316.98

Full DSR item description

Centering and shuttering including strutting, propping etc. and removal of form for - Foundations, footings, bases of columns, etc. for mass concrete

Coefficients are taken from the CPWD analysis of rates for DSR Civil 2023. Basic rates are revised by cost index and correction slips, so multiply these quantities by current market rates rather than assuming a published rate is still live.