Centering & ShutteringCPWD DSR Civil 2023 · Item 5.9.3

Shuttering — Suspended floors, roofs, landings, balconies and

Analysed rate
₹776.89per sqm
CPWD analyses this item over 135.0019 sqm; the batch total is ₹1,04,881.33.

All coefficients below are per 135.0019 sqm of finished work. This is the complete analysis for the item — every material, labour trade, machine, carriage line and sub-analysis it consumes.

Complete analysis

Materials 2

IngredientCoefficientUnitRate (₹)Amount (₹)
Adjustable span ESO+SI (2.35-3.40) 1.063 each 1,540.00 1,637.02
Adjustable telescopic prop 3 m (2.02-3.75 m) 1.275 each 1,051.00 1,340.03

Labour 2

IngredientCoefficientUnitRate (₹)Amount (₹)
Fitter (grade 1) 30 day 897.00 26,910.00
Beldar 60 day 736.00 44,160.00

Sub-Analysis (derived item) 1

IngredientCoefficientUnitRate (₹)Amount (₹)
[Sub-Item] 10.1 92.055 kg 117.35 10,802.65

Sundries & Lump Sum 4

IngredientCoefficientUnitRate (₹)Amount (₹)
Sundries 221 L.S. 2.27 501.67
Carriage 1300 L.S. 2.27 2,951.00
Sundries 780 L.S. 2.27 1,770.60
Sundries 497 L.S. 2.27 1,128.19

Analysed rate

Sub-total (materials, labour, machinery, sundries)₹91,201.16
Add contractor's profit & overheads @ 15%₹13,680.17
Analysed rate for the full 135.0019 sqm batch₹1,04,881.33
Rate per sqm₹776.89

Full DSR item description

Centering and shuttering including strutting, propping etc. and removal of form for - Suspended floors, roofs, landings, balconies and access platform

Coefficients are taken from the CPWD analysis of rates for DSR Civil 2023. Basic rates are revised by cost index and correction slips, so multiply these quantities by current market rates rather than assuming a published rate is still live.

← All material coefficients|Browse CPWD DSR Civil 2023|How rate analysis works