Centering & ShutteringCPWD DSR Civil 2023 · Item 5.9.2

Shuttering — Walls including attached pilasters, butteresses,

Analysed rate
₹681.03per Unit
CPWD analyses this item over 15 Unit; the batch total is ₹10,215.42.

All coefficients below are per 15 Unit of finished work. This is the complete analysis for the item — every material, labour trade, machine, carriage line and sub-analysis it consumes.

Complete analysis

Materials 5

IngredientCoefficientUnitRate (₹)Amount (₹)
Wall form panel 1250x500 mm 0.51 each 900.00 459.00
100 mm channel shoulder 2.5 m long 0.13 each 950.00 123.50
Double clip (bridge clip) 0.51 each 80.00 40.80
Single clip 0.255 each 64.00 16.32
M.S. tube 40 mm dia 0.68 metre 225.00 153.00

Labour 2

IngredientCoefficientUnitRate (₹)Amount (₹)
Fitter (grade 1) 3.5 day 897.00 3,139.50
Beldar 6 day 736.00 4,416.00

Sundries & Lump Sum 4

IngredientCoefficientUnitRate (₹)Amount (₹)
Sundries 27.62 L.S. 2.27 62.70
Carriage 78 L.S. 2.27 177.06
Sundries 78 L.S. 2.27 177.06
Sundries 52 L.S. 2.27 118.04

Analysed rate

Sub-total (materials, labour, machinery, sundries)₹8,882.98
Add contractor's profit & overheads @ 15%₹1,332.45
Analysed rate for the full 15 Unit batch₹10,215.42
Rate per Unit₹681.03

Full DSR item description

Centering and shuttering including strutting, propping etc. and removal of form for - Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.

Coefficients are taken from the CPWD analysis of rates for DSR Civil 2023. Basic rates are revised by cost index and correction slips, so multiply these quantities by current market rates rather than assuming a published rate is still live.

← All material coefficients|Browse CPWD DSR Civil 2023|How rate analysis works