Wood WorkCPWD DSR Civil 2023 · Item 9.3.1

Wood Work — Sal wood

Analysed rate
₹84,679.10per Unit
CPWD analyses this item over 0.158 Unit; the batch total is ₹13,379.30.

All coefficients below are per 0.158 Unit of finished work. This is the complete analysis for the item — every material, labour trade, machine, carriage line and sub-analysis it consumes.

Major materials at a glance

Timber
16.610 cudm
Sal wood in scantling

Complete analysis

Materials 1

IngredientCoefficientUnitRate (₹)Amount (₹)
Sal wood in scantling Timber 16.6 10 cudm 600.00 9,960.00

Labour 2

IngredientCoefficientUnitRate (₹)Amount (₹)
Carpenter 2nd class 1 day 816.00 816.00
Beldar 1 day 736.00 736.00

Carriage 1

IngredientCoefficientUnitRate (₹)Amount (₹)
Carriage of Timber 0.166 cum lead-dependent

Sundries & Lump Sum 1

IngredientCoefficientUnitRate (₹)Amount (₹)
Sundries 53.82 L.S. 2.27 122.17

Analysed rate

Sub-total (materials, labour, machinery, sundries)₹11,634.17
Add contractor's profit & overheads @ 15%₹1,745.13
Analysed rate for the full 0.158 Unit batch₹13,379.30
Rate per Unit₹84,679.10

1 carriage line is excluded from this total. CPWD leaves carriage rates blank because they depend on lead distance and station, so they must be priced locally and added. The analysed rate above is therefore the works cost before carriage, not a complete tender rate.

Full DSR item description

Providing wood work in frames of false ceiling, partitions etc. sawn and fixed in position with necessary stainless steel screws etc. - Sal wood

Coefficients are taken from the CPWD analysis of rates for DSR Civil 2023. Basic rates are revised by cost index and correction slips, so multiply these quantities by current market rates rather than assuming a published rate is still live.

← All material coefficients|Browse CPWD DSR Civil 2023|How rate analysis works