BOQ — Bill of Quantities

BOQ stands for Bill of Quantities — an itemised list of every item of work in a project, each with its description, unit, measured quantity and rate, used to tender the work and then to pay for it.

What a BOQ is for

A BOQ does three jobs across the life of a project, and it is the same document each time.

  1. Tendering on a like-for-like basis. Every bidder prices the same list of items and quantities, so the bids can actually be compared. Without it, one contractor's lump sum is not comparable to another's.
  2. Forming the contract. The priced BOQ becomes the schedule of the agreement — the rates in it are what the contractor is entitled to for the work described.
  3. Paying for work. Quantities are re-measured as the work is built and paid at the agreed rates. This is why a BOQ item's description matters as much as its rate: the description defines what is covered.

What a BOQ item contains

FieldExample
Item number6.1.2
DescriptionBrick work with common burnt clay F.P.S. bricks of class designation 7.5 in foundation and plinth in cement mortar 1:6
Unitcum
Quantity124.60
Rate₹7,234.55
Amount₹9,01,425.13

On a CPWD job the description and rate normally come straight from the DSR, and only the quantity is yours. That is what makes a government BOQ faster to prepare than a private one — and what makes an item the schedule does not carry into a piece of work in itself.

BOQ, estimate and abstract

These three overlap enough to be worth separating.

  • An estimate is prepared before tender to establish a cost. It may be approximate — per square foot, or on plinth area — or fully detailed.
  • A BOQ is the itemised, measured list issued for tender and used to contract. A detailed estimate becomes a BOQ once its quantities are firm and its items are the ones being tendered.
  • An abstract is the summary of value at a point in time — items, quantities executed, rates and amounts — produced from the measurement book for each running account bill.

What makes a BOQ go wrong

  • Descriptions edited from the schedule. Trimming a DSR description to make it fit a column narrows the scope of the item, and the narrowed version is the one in the contract.
  • Missing items. Anything not in the BOQ has to be added later as an extra item, with a rate worked out and sanctioned — see the NS item rate analysis guide.
  • Quantities that do not reconcile to the drawings. The first re-measurement finds it, usually in the form of a deviation beyond the permitted limit.
  • Mixed units. An item measured in sqm in the BOQ and in cum on site is a dispute, not a rounding difference.

Frequently asked questions

What is the full form of BOQ?

+
BOQ stands for Bill of Quantities — the itemised list of work items, with units, quantities and rates, that a project is tendered and paid against.

What is the difference between a BOQ and an estimate?

+
An estimate establishes a likely cost before tender and may be approximate. A BOQ is the firm, itemised, measured list issued for tender and used as the contract schedule. A detailed estimate becomes a BOQ once its items and quantities are the ones being tendered.

Who prepares the BOQ?

+
The employer's side — the department, its consultant or the quantity surveyor — prepares and issues it. Bidders price it; they do not write it. That is what keeps the bids comparable.

What happens if an item is missing from the BOQ?

+
It becomes an extra item. The work still has to be done, but a rate has to be worked out and sanctioned by the competent authority before it can be paid, which is slower than having had it in the BOQ.

Last reviewed 2026-08-19. This is general guidance on CPWD practice, not a substitute for your own agreement and the departmental rules in force — where the two differ, the agreement governs.