₹913.89 per Sqm
Rates include GST and contractor’s profit & overheads (15%), effective 01-08-2024.
Applying stamping finish to the top surface of freshly laid plain/reinforced cement concrete of specified grade in porticos,sidewalks, driveways, pool decks and open yards as per direction of the Engineer-in-Charge. The process shall include thefollowing:- The concrete shall be placed and screeded to the finished grade, and floated to a uniform surface by using standardfinishing techniques. The approved color hardener @ 2.7 kg/sqm shall be applied evenly to the surface of the fresh concreteby the dry shake method by sprinkling in two or more shakes, floated after each shake and trowelled only after the finalfloating. The approved release agent @ 0.113 kg/sqm shall be applied evenly to the trowelled surface before stamping orthe said release agent can be applied to the flexible polyurethane stamp moulds of approved design and in required sizes toachieve final stamped pattern. These stampings shall be placed on the surface of concrete in three to four pieces at a timeand tapped gently with rammers of sufficient size & weight to leave proper stamp marks and the process repeated for theremaining concrete surface till the whole surface to be stamped is completed within the time while concrete is in plasticstage of setting.
After stamping, the curing shall be done as per manufactures specifications. After initial curing the imprinted joints shall begrouted using cement slurry mixed with color hardener as per the requirement. The surface shall be sealed by applyingacrylic based sealer not less than 0.167 litre/sqm.on finished surface.
The construction joints shall be provided by groove cutting of size 4mm x 20mm in panel size 3m x 3 m or lesser as per thesite conditions and filling the same with 10 mm baker rod and providing and laying (PU) Polyurethane based joint sealer ofapproved make as per manufacturer’s specifications and finished by applying Polyurethane resin based top protective clearcoat of minimum 80 micron applied with rollers on properly cured and dry clean surface. (Cost of concrete for flooring is notincluded in this item which shall be paid separately.)
Build a BOQ with Ladakh SoR rates · All items in New Technologies & Materials