Ladakh SoR 2024: Chapter 15 — Dismentling And Demolishing

Rates include GST and contractor’s profit & overheads (15%), effective 01-08-2024.

15.1Demolishing lime concrete manually/ by mechanical means and disposal of material within 50 metres lead as per direction of Engineer-…₹689.71 / Cum 15.2.1Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer…₹1,974.16 / Cum 15.2.2Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer…₹1,218.08 / Cum 15.3Demolishing R.C.C. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50…₹2,880.07 / Cum 15.4Demolishing R.B. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50…₹2,574.65 / Cum 15.5Extra for cutting reinforcement bars manually/ by mechanical means in R.C.C. or R.B. work (Payment shall be made on the cross sectional…₹1,080.25 / Cum 15.6Extra for scrapping, cleaning and straightening reinforcement from R.C.C. or R.B. work.₹8.21 / Kg 15.7.1Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material…₹571.22 / Cum 15.7.2Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material…₹1,443.06 / Cum 15.7.3Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material…₹689.71 / Cum 15.7.4Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material…₹1,668.74 / Cum 15.8.1Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m (stacks of cleaned bricks shall be measured): From…₹3,852.80 / 1000 Nos 15.8.2Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m (stacks of cleaned bricks shall be measured): From…₹4,509.86 / 1000 Nos 15.8.3Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m (stacks of cleaned bricks shall be measured): From…₹5,689.25 / 1000 Nos 15.9.2Demolishing stone rubble masonry manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable…₹1,991.43 / Cum 15.10.1Dismantling dressed stone work ashlar face stone work, marble work or precast concrete work manually/ by mechanical means including…₹1,187.28 / Cum 15.10.2Dismantling dressed stone work ashlar face stone work, marble work or precast concrete work manually/ by mechanical means including…₹2,330.02 / Cum 15.11.1Removing mortar from and cleaning stones and concrete articles (net quantity concrete articles (net quantity of stacks of cleaned materials…₹398.10 / Cum 15.11.2Removing mortar from and cleaning stones and concrete articles (net quantity concrete articles (net quantity of stacks of cleaned materials…₹568.91 / Cum 15.12.1Dismantling doors, windows and clerestory windows (steel or wood) shutter including chowkhats, architrave, holdfasts etc. complete and…₹333.37 / each 15.12.2Dismantling doors, windows and clerestory windows (steel or wood) shutter including chowkhats, architrave, holdfasts etc. complete and…₹432.19 / each 15.13.1Taking out doors, windows and clerestory window shutters (steel or wood) including stacking within 50 metres lead Of area 3 sq. metres and…₹130.22 / each 15.13.2Taking out doors, windows and clerestory window shutters (steel or wood) including stacking within 50 metres lead Of area beyond 3 sq.…₹172.85 / each 15.14.1Dismantling wood work in frames, trusses, purlins and rafters up to 10 metres span and 5 metres height including stacking the material…₹4,163.81 / each 15.14.2Dismantling wood work in frames, trusses, purlins and rafters up to 10 metres span and 5 metres height including stacking the material…₹16.65 / metre 15.15.1Extra for dismantling trusses, rafters, purlins etc. of wood work for every additional span of one metre or part thereof beyond 10 metres :…₹548.18 / cum per metre span 15.15.2Extra for dismantling trusses, rafters, purlins etc. of wood work for every additional span of one metre or part thereof beyond 10 metres :…₹1.56 / cum per metre span 15.16.1Extra for dismantling trusses, rafters, purlins etc. of wood work for every additional height of one metre or part thereof beyond 5 metres…₹777.92 / cum per metre span 15.16.2Extra for dismantling trusses, rafters, purlins etc. of wood work for every additional height of one metre or part thereof beyond 5 metres…₹3.05 / cum per metre span 15.17.1Dismantling steel work in single sections including dismembering and stacking within 50 metres lead in: R.S. Joists₹2.95 / Kg 15.17.2Dismantling steel work in single sections including dismembering and stacking within 50 metres lead in: Channels, angles, tees and flats₹2.04 / Kg 15.18Dismantling steel work in built up sections in angles, tees, flats and channels including all gusset plates, bolts, nuts, cutting rivets,…₹5.06 / Kg 15.19Dismantling steel work manually/ by mechanical means in built up sections without dismembering and stacking within 50 metres lead as per…₹3.19 / Kg 15.20Extra for dismantling trusses, rafters, purlins etc. of steel work for every additional span of one metre or part thereof beyond 10 metres₹0.72 / Kg Per metre span 15.21Extra for dismantling trusses, rafters, purlins etc. of steel work for every additional height of one metre or part thereof beyond 5 metres.₹0.72 / Kg Per metre height 15.22Extra for marking of structural steel work required to be re-erected.₹4.23 / Kg 15.23.1Dismantling tile work in floors and roofs laid in cement mortar including stacking material within 50 metres lead. For thickness of tiles…₹66.03 / Sqm 15.23.2Dismantling tile work in floors and roofs laid in cement mortar including stacking material within 50 metres lead. For thickness of tiles…₹104.44 / Sqm 15.24Demolishing dry brick pitching in floors, drains etc. including stacking of serviceable material and disposal of unserviceable material…₹1,068.76 / Sqm 15.25Dismantling stone slab flooring laid in cement mortar including stacking of serviceable material and disposal of unserviceable material…₹216.46 / Sqm 15.26Demolishing brick tile covering in terracing including stacking of serviceable material and disposal of unserviceable material within 50…₹96.90 / Sqm 15.27Demolishing mud phaska in terracing and disposal of material within 50 metres lead.₹740.50 / Sqm 15.28.1Dismantling roofing including ridges, hips, valleys and gutters etc., and stacking the material within 50 metres lead of: G.S. Sheet₹147.75 / Sqm 15.28.2Dismantling roofing including ridges, hips, valleys and gutters etc., and stacking the material within 50 metres lead of: Asbestos cement…₹68.59 / Sqm 15.29Dismantling stone slab roofing over wooden karries or R.C.C. battens (dismantling karries and battens to be paid for separately), including…₹2,164.63 / Sqm 15.30Dismantling jack arch roofing and floors including stacking of serviceable material and disposal of unserviceable material within 50 metres…₹206.31 / Sqm 15.31Dismantling tiled roofing with battens, boarding etc. complete including stacking of serviceable material and disposal of unserviceable…₹170.75 / Sqm 15.32Demolishing thatch roofing including mats, bamboo, jaffari etc. complete including stacking of serviceable material and disposal of…₹47.13 / Sqm 15.33Dismantling wooden ballies in posts and struts including stacking within 50metres lead.₹16.97 / metre 15.34.1Dismantling and stacking within 50 metres lead, fencing posts or struts including all earth work and dismantling of concrete etc. in base…₹206.28 / each 15.34.2Dismantling and stacking within 50 metres lead, fencing posts or struts including all earth work and dismantling of concrete etc. in base…₹228.51 / each 15.35Cutting ballies or wooden posts of fencing at the point of projection above the concrete or ground and stacking the same within 50 metres…₹16.27 / each 15.36Dismantling barbed wire or flexible wire rope in fencing including making rolls and stacking within 50 metres lead.₹29.83 / Kg 15.37Dismantling wooden trellis work excluding frames but including stacking the serviceable material within 50 metres lead.₹54.89 / Sqm 15.38Dismantling expanded metal or I.R.C. fabrics with necessary battens and beading including stacking the serviceable material within 50…₹64.51 / Sqm 15.39.1Dismantling wooden boardings in lining of walls and partitions, excluding supporting members but including stacking within 50 metres lead :…₹54.08 / Sqm 15.39.2Dismantling wooden boardings in lining of walls and partitions, excluding supporting members but including stacking within 50 metres lead :…₹69.15 / Sqm 15.39.3Dismantling wooden boardings in lining of walls and partitions, excluding supporting members but including stacking within 50 metres lead :…₹80.21 / Sqm 15.40.1Dismantling precast concrete or stone slabs in walls, partition walls etc. including stacking within 50 metres lead : Thickness up to 40 mm₹241.04 / Sqm 15.40.2Dismantling precast concrete or stone slabs in walls, partition walls etc. including stacking within 50 metres lead : Thickness above 40 mm…₹359.28 / Sqm 15.41Dismantling cement asbestos or other hard board ceiling or partition walls including stacking of serviceable materials and disposal of…₹51.66 / Sqm 15.42.1Dismantling C.I. or asbestos rain water pipe with fittings and clamps including stacking the material within 50 metres lead : 75 to 80 mm…₹61.30 / metre 15.42.2Dismantling C.I. or asbestos rain water pipe with fittings and clamps including stacking the material within 50 metres lead : 100 mm dia…₹63.25 / metre 15.42.3Dismantling C.I. or asbestos rain water pipe with fittings and clamps including stacking the material within 50 metres lead : 150 mm dia…₹65.14 / metre 15.43.1Dismantling manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50…₹179.04 / Sqm 15.43.2Dismantling manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50…₹350.29 / Sqm 15.44.1Dismantling G.I. pipes (external work) including excavation and refilling trenches after taking out the pipes, manually/ by mechanical…₹139.81 / metre 15.44.2Dismantling G.I. pipes (external work) including excavation and refilling trenches after taking out the pipes, manually/ by mechanical…₹139.81 / metre 15.45.1Dismantling C.I. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead…₹367.25 / metre 15.45.2Dismantling C.I. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead…₹481.01 / metre 15.45.3Dismantling C.I. pipes including excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking lead…₹630.58 / metre 15.46.1Dismantling steel cylinder R.C. pipes excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking…₹596.13 / metre 15.46.2Dismantling steel cylinder R.C. pipes excavation and refilling trenches after taking out the pipes, manually/ by mechanical means breaking…₹1,571.50 / metre 15.47.1Dismantling asbestos cement pressure pipes including excavation and refilling trenches after taking out the pipes manually/ by mechanical…₹268.94 / metre 15.47.2Dismantling asbestos cement pressure pipes including excavation and refilling trenches after taking out the pipes manually/ by mechanical…₹326.52 / metre 15.48Taking out C.I. cover with frame from R.C.C. top slab of manholes of various sizes including demolishing of R.C.C. work manually/ by…₹574.80 / each 15.49Taking out C.I. cover with frame from R.C.C. top slab of inspection chambers of various sizes including demolishing of R.C.C. work…₹336.59 / each 15.50Dismantling of R.C.C. spun vent shaft including excavating the cement concrete pit completely, taking out the shaft, refilling the…₹3,953.59 / each 15.51Dismantling of road gully chamber of various sizes including C.I. grating with frame including stacking of useful materials near the site…₹785.91 / each 15.52Dismantling of flushing cistern of all types (C.I./PVC/Vitrious China) including stacking of useful materials near the site and disposal of…₹811.03 / each 15.53.1Dismantling of C.I. sluice valve including stacking of useful materials within a lead of 50 metres Up to 150 mm diametre₹295.12 / each 15.53.2Dismantling of C.I. sluice valve including stacking of useful materials within a lead of 50 metres Above 150 mm diametre₹1,067.96 / each 15.54Dismantling of spindle fire hydrant including stacking of useful materials within 50 metres lead.₹655.16 / each 15.55.1Dismantling of cement concrete platform along with curtain walls and base concrete etc. including stacking of useful materials near the…₹894.39 / each 15.55.2Dismantling of cement concrete platform along with curtain walls and base concrete etc. including stacking of useful materials near the…₹1,592.05 / each 15.55.3Dismantling of cement concrete platform along with curtain walls and base concrete etc. including stacking of useful materials near the…₹1,941.64 / each 15.56Dismantling old plaster or skirting raking out joints and cleaning the surface for plaster including disposal of rubbish to the dumping…₹44.58 / Sqm 15.57Dismantling aluminium/ Gypsum partitions, doors, windows, fixed glazing and fal ceiling including disposal of unserviceable material and…₹51.68 / Sqm 15.58Demolishing R.C.C. work by mechanical means and stockpiling at designated locations and disposal of dismantled materials up to a lead of 1…₹2,630.27 / Cum 15.59Dismantling of flexible pavement (bituminous courses) by mechanical means and disposal of dismantled material up to a lead of 1 kilometre,…₹379.28 / Cum 15.60Disposal of building rubbish / malba / similar unserviceable, dismantled or waste materials by mechanical means, including loading,…₹226.40 / Cum